The dashboard collects the key measures about the project.
To be used to control the project, and compare with others. These measures will not be used to grade the project.
We consider two phases:
-New development: From project start (april 5) to delivery of version 0 (release 0, may 28)
-Corrective Maintenance: fix of defects (if any) (may 28 to june 4)
Report effort figures from the timesheet or timesheetCR document, compute size from the source code.
New development (release 0 -- april 5 to may 28)
Measure
Value
effort E (report here effort in person hours, for New development, from timesheet)
247
size S (report here size in LOC of all code written, excluding test cases)
3936
productivity = S/E
15.94
defects before release D_before (number of defects found and fixed before may 28)
8
Corrective Maintenance (release 1 -- may 28 to june 4)
Measure
Value
effort for non-quality ENQ (effort for release 1, or effort to fix defects found when running official acceptance tests)
9
effort for non quality, relative = ENQ / E
0.0364
defects after release D (number of defects found running official acceptance tests and fixed in release 1)
8
defects before release vs defects after release = D/D_before