-
Notifications
You must be signed in to change notification settings - Fork 10
/
Copy pathORNL-3369.txt
7902 lines (6200 loc) · 258 KB
/
ORNL-3369.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
ORNL=3369
UC-80 — Reactor Technology
MO LTEN-SALT REACTOR PROGRAM
SEMIANNUAL PROGRESS REPORT
FOR PERIOD ENDING AUGUST 31, 1962
OAK RIDGE NATIONAL LABORATORY
operated by
UNION CARBIDE CORPORATION
for the
U.S. ATOMIC ENERGY COMMISSION
DISCLAIMER
This report was prepared as an account of work sponsored by an
agency of the United States Government. Neither the United States
Government nor any agency Thereof, nor any of their employees,
makes any warranty, express or implied, or assumes any legal
liability or responsibility for the accuracy, completeness, or
usefulness of any information, apparatus, product, or process
disclosed, or represents that its use would not infringe privately
owned rights. Reference herein to any specific commercial product,
process, or service by trade name, trademark, manufacturer, or
otherwise does not necessarily constitute or imply its endorsement,
recommendation, or favoring by the United States Government or any
agency thereof. The views and opinions of authors expressed herein
do not necessarily state or reflect those of the United States
Government or any agency thereof.
DISCLAIMER
Portions of this document may be illegible In
electronic image products. Images are produced
from the best available original document.
Printed in USA. Price: $2.75 Available from the
Office of Technical Services
U. S. Department of Commerce
Washington 25, D. C,
LEGAL NOTICE
This report was prepared as an account of Government sponsored work. Neither the United States,
nor the Commission, nor any person acting on behalf of the Commission:
A. Makes any warranty or representation, expressed or implied, with respect to the accuracy,
completeness, or usefulness of the information contained in this report, or that the use of
any information, apparatus, method, or process disclosed in this report may not infringe
privately owned rights; or
B. Assumes any liabilities with respect to the use of, or for damages resulting from the use of
any information, apparatus, method, or process disclosed in this report.
As used in the above, ‘“person acting on behalf of the Commission’’ includes any employee or
contractor of the Commission, or employee of such contractor, to the extent that such employee
or contractor of the Commission, or employee of such contractor prepares, disseminates, or
provides access to, any information pursuant to his employment or contract with the Commission,
or his employment with such contractor.
| B A
ORNL-3369
Contracf No. W-7405-eng-26
MOLTEN-SALT REACTOR PROGRAM
SEMIANNUAL PROGRESS REPORT
For Period Ending August 31, 1962
R. B. Briggs, Program Director
Date Issued
DEC 12 1962
OAK RIDGE NATTONAL LABORATORY
Oak Ridge, Tennessee
. operated by
UNION CARBIDE CORPORATION
for the
U.S. ATOMIC ENERGY COMMISSION
e
- THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
iii
SUMMARY
Part 1. MSRE Design, Engineering Analysis,
and Component Development
1. MSRE Design
No significant changes in design concept or in detail of any component
or system were made. Design work was essentially completed, and a design
report giving all engineering calculations and analyses of the systems is
being compiled. The remaining design work involves primarily the incor-
poration of results of development work into the final drawings.
Work on the major building modifications is proceeding as scheduled,
- and the estimated completion date is October 15, 1962. A contract was
- (w awarded for construction work required outside the building, and this work
too is to be completed soon. It consists of construction of the exhaust
filter house, the cooling towers, the underground piping, and the inlet
filter house.
Materials procurement is on schedule with the exception of the core
graphite, delivery of which is now expected November 1, 1962. Fabrication
of components is approximately 50% complete and on schedule.
The basic instrument criteria and the control philosophy were estab-
lished. The layout of the instrument and controls system was established,
and the design of control-panel interconnection facilities is under way.
Designs for 30 of the 42 instrument panel sections required in the
MSRE system are complete. Fabrication of these panels by the ORNL shops
is under way.
) A freeze-valve test facility was completed and placed in operation.
./' .
A The selection of detectors for the process and personnel radiation
monitoring system is approximately 80% complete.
Procurement of a data-handling system was initiated. Specifications
were prepared and procurement initiated for 80% of the components required
in the process instrument system.
2. MSRE Reactor Analysis
Conceivable reactivity accidents were analyzed to permit evaluation
of reactor safety. Most of the calculations were done using Murgatroyd,
a digital kinetics program, but some analog analyses were also used. None
of the accidents analyzed led to-catastrophic failure of the reactor.
Undesirably high temperatures were predicted, however, for circumstances
associated with extreme cold-slug accidents, premature criticality during
filling, and uncontrolled rod withdrawal.
iv
Criticality and flux calculations were revised to correspond to the
latest fuel composition and the detailed design of the core. Calculations
were done for a core model consisting of 19 regions with different volume
fractions of fuel, graphite, and INOR-8. The clean critical concentration
for the reactor fueled with salt containing no thorium was calculated to
be 0.15 mole % uranium (93% UZ3%),
High-energy fluxes were also calculated. At a reactor power of 10
Mw, the maximum flux was about 1.3 X 1013 neutrons/cmZ.sec for neutrons
having energies greater than 1 Mev; for neutrons having energies greater
than 0.1 Mev, the maximum flux was about 3.7 x 102 neutrons/cmZ-sec.
_ Fluxes and power densities from the Equipoise calculations were used,
together with the detailed flow distribution in the MSRE core, to predict
the gross temperature distributions in the fuel and graphite. At 10 Mw,
with fuel entering the core at 1175°F, fuel in the hottest channels left
the reactor at 1261°F. Under the same conditions the peak graphite tem-
perature was 1296°F, A low-temperature region existed through the center
of the core where the fuel velocity was above average.
The nuclear average temperature, defined as that uniform temperature
which results in the same reactivity as the actual distribution, was cal-
culated for the fuel and for the graphite. Perturbation theory was em-
ployed, using coefficients from the Equipoise calculations. At 10 Mw,
with the fuel inlet at 1175°F and the mixed-fuel outlet temperature at
1225°F, the nuclear average temperatures for the fuel and graphite were
1213 and 1257°F, respectively.
Importance-averaged temperature coefficients of reactivity were cal-
culated for the case of fuel containing no thorium. The results were
A hs x 1075 and -T7.27 x 1072 (8k/k)/°F for the Tuel and the graphite,
regpeetively.
Power coefficients of reactivity were calculated from the nuclear
average temperatures and reactivity coefficients. This quantity, defined
as the reactivity adjustment required as the power is raised, depends upon
which temperature is used as the control parameter. If the mean of the
fuel inlet and outlet temperatures were held constant, the power coef-
ficient of reactivity would be -L4.7 x 10™* (8k/k)/Mw. If the fuel outlet
temperature were held constant, the power coefficient would be only
-1.8 x 107% (dk/k)/Mw.
Effective delayed-neutron fractions were calculated, taking into
account the delayed-neutron energies and the spatial source distributions
in a one-region model of the core. For a total yield of 0.0064 delayed
neutron per fission neutron, the effective fraction in the static core
was 0.0067. With fuel circulating at 1200 gpm, the effective steady-state
fraction was 0.0036. '
Preliminary tests were made of a new IBM-7T090 program for the analysis
of simulated power transients, based on a simplified space-dependent ki-
netics model. This program calculates fuel and graphite temperature
Iz i
7 A\
LY
&\
[ A
e
I“ &
L
distributions during transients and uses the nuclear-average-temperature
concept to relate temperature changes to the reactivity.
3. Component Development
Measurements were made on INOR-8 freeze flanges for 5-in.-diam sched-
4LO pipe under several different steady-state and transient conditions with
both an octagonal and an oval nickel ring gasket. The following conclusions
were drawn from these measurements: the flange joint design appears to
be satisfactory from an accumulated thermal stress standpoint after 43
cycles from room temperature to 1300°F and higher; the thermal distortion
of the flanges is small in the operating range and is not of a nature to
cause the flanges to separate at the seal; thermal cycling does not cause
the gas leakage rate to increase above an acceptable level; the flange
Joint will not form a frozen plug in the pipe under no-flow conditions if
the pipe heaters are kept on; the thermal and distortion properties of the
INOR-8 flanges are superior to those of the Inconel flanges tested previ-
ously; and thermal cycling of one flange did not affect its ability to
seal with a new flange,
A full-scale conceptual model of the control rod and drive unit was
assembled and tested under operating conditions for over 24,000 cycles.
Difficulty with & bushing was solved by replacement with bail bearings.
Over-all operation was satisfactory.
Evaluation of a removable 5-in. pipe heater insulated with hardboard
and mineral wool indicated excellent performance except for the tendency
to produce dust after high-temperature operation. Nuclear activation
analyses of insulating materials indicated that the dust would present a
problem of air-borne activity during maintenance. Another unit, con-
structed of foamed fused-silica, was better with respect to dusting but
had an excessive heat loss. An improved fused-silica pipe heater, incor-
porating some canned hardboard is being fabricated. An all-metal reflec-
tive type of unit was procured for evaluation.
The prototype cooling bayonets for removing fuel afterheat from the
drain tanks were thermally shock tested 384 times without failure. Reactor-
grade thermocouples were still intact after 6 cycles, whereas other types
of thermocouples failed in fewer cycles.
Detail drawings of essentially all the components and instrumentation
of the sampling and enriching system were finished, and construction of
a mockup was started. The sampling-capsule access-chamber mockup passed
the hydrostatic test requirements, and hot cell removal of a sample from
the capsule was demonstrated.
The full-scale MSRE core model was operated at 85°F with water to
make preliminary measurements of the velocity distribution, heat transfer
coefficients, and solids-handling characteristics. The velocity distri-
bution in the lower core wall-cooling annulus was found to be uniform
around the circumference, indicating that the flow into the lower head
was also uniform. The heat transfer coefficients in the lower head agreed
Vi
with the predicted values, except near the axis, where the measurements
were irregular because of the random flow. Preliminary measurements of
the solids distribution in the lower head indicated that solids which do
remain in the core tend to collect near the drain line at the center. It
appeared, however, that they would not plug the drain line.
The engineering test loop was revised to include a graphite container
and INOR-8 pipe and was placed in operation with a newly made zirconium-
free coolant salt. Information was obtained of the operating character-
istics of the frozen seal in the graphite container. It was found that a
salt mist existed in the pump-bowl gas space that led to some difficulties
with frozen salt deposits, but no such mist was found in the drain-tank
gas space. After 1500 hr of operation with the empty container, graphite /
was installed, vacuum pretreated at 1200°F, and prepared for flushing with
salt that had been treated with HF to lower its oxide content.
Design and construction of equipment for opening and closing freeze-
f'lange joints was completed, and procedure testing was started. A peri-
scope was purchased for use with this equipment. The design of a portahle
shield facility for semidirect maintenance operations is 60% complete.
Tt is a motorized unit with the appropriate openings and lighting for
specific operations.
Six prototype brazed joints were fabricated for quality evaluation
"using the equipment and general techniques required for remote operation.
A similar joint was removed from a loop for metallurgical examination
after 6780 hr at 1250°F and exposure to fuel salt for 123 hr.
The design of the overflow-line disconnect to the fuel pump was com-
pleted, and a carbon-steel prototype was built and successfully rough-
tested as a demonstration of the concept. An INOR-8 model was constructed:
for finel testing.
The design drawings for the coolant pump, the drive motors of the
fuel and coolant pumps, and the lubrication stands were approved. The
assembly of the rotary element and the fabrication and assembly of the
hot test stand for the prototype fuel pump were completed and testing was
started. Acceptable INOR-8 castings of impellers and volutes for the fuel
and coolant pumps and dished heads for the pump tanks were obtained. Fab-
rication of all components required for the reactor pumps was initiated.
A prototype model of the two-level conductivity-type liquid-level
probe being developed for use in measurement of level in the MSRE storage
tanks was constructed and is being tested.
Developmental testing of an element for continuous measurements of
the molten-salt level in the reactor pumps was continued. The maximum
variation recorded during a four-month test was 0.1 in., and there has
been no significant degradation in performance characteristics to date.
Investigations of single-channel thermocouple alarm switches for use
in freeze-flange and freeze-valve monitoring continued. A commerical
system is undergoing field .tests.
0
vii
Development of the mercury-jet-commitator thermocouple-scanning
system is continuing. Modifications of the switch were made to reduce
spurious noise generation. An alarm discriminator was designed and con-
structed. A complete system was assembled and tested.
Testing of mechanical attachments for use on radiator tubes in the
MSRE was resumed after modifying the test apparatus. The differential
between indicated inner and outer wall temperatures under simulated opera-
ting conditions was reduced to 9°F when the thermocouple was insulated
with Fiberfrax paper and Thermom cement was applied between the thermo-
couple and the tube wall.
Six Inconel-sheathed MgO-insulated Chromel-Alumel thermocouples are
being tested in 1200 to 1250°F air. The observed drift in all units
after 5000 hr of operation was less than *2°F,
Ten MSRE-prototype wall-mounted thermocouples were exposed to fast
temperature transients on the drain-tank bayonet-cooler testing facility.
One thermocouple failed immediately. The remaining nine units have with-
stood repeated raplid temperature changes.
Results of tests of thermocouples installed on an MSRE-prototype
freeze valve indicate that either 1/8-in.-OD duplex or 1/16-in.-0D single-
conductor thermocouples will measure wall temperatures on the freeze valve
within the required accuracy and will withstand the temperature transients
inherent in this application. No significant difference in the perform-
ance or durability of the units was noted.
A six-circuit radiation-resistant thermocouple-disconnect assembly
was fabricated and tested in a remote-maintenance facility. The discon-
nect is simpler in construction than the assembly described previously
and is more compatible with MSRE requirements.
Part 2. Materials Studies
4., Metallurgy
Tests were completed for determining the corrosive effect of CFa
vapor on INOR-8 immersed in fuel salt at 1112 and 1292°F. Results of
these indicate that CF4 vapor is effectively nonreactive toward INOR-8
at 1112°F but that minor attack may be promoted by CF; in the presence
of fluoride salts at 1292°F.
A final design and a welding procedure were established for the tube-
to-tube sheet joints of the MSRE heat exchanger. The final design pro-
vides for ultrasonic inspection. In order to demonstrate the welding and
inspection procedures, a 96-joint test assembly was successfully fabri-
cated and inspected by radiographic and ultrasonic Lamb-wave techniques.
Brazing procedures for remotely preparing INOR-8 pipe joints were demon-
strated by the fabrication of six joints. Only minor unbonded areas
were found in these by ultrasonic inspection.
L
viii
Additional mechanical properties data were accumulated for INOR-8,
including thermal fatigue data at 1250 to 1600°F. Stress relieving was
found to improve the elevated-temperature stress-rupture properties of
weldments. Evaluation studies of the mechanical properties of heats of
INOR-8 procured for MSRE construction were started.
Grade TS-281 graphite, considered representative of MSRE material,
was found to be more porous than experimentally made samples of similar
graphite; however, it met design requirements. Specimens of TS-281 were
permeated to 0.2% of the bulk volume in the standard permeation tests.
Oxygen contamination was purged from R-0025-grade graphite with the de-
composition products of NH4F.HF at temperatures as low as 392°F. Exposure
of INOR-8 specimens to this environment at temperatures varying from 392
to 1300°F resulted in minimum attack at 752°F.
Sintering studies were begun to develop procedures for fabricating
Gdz03 and Gdz03-Alz0sz cylinders for MSRE control rods. The shrinkage
characteristics and bulk density changes as a function of green density
were determined for Gdz0s pellets that were fired at 1750°C in hydrogen.
5. In-Pile Tests
Two molten-salt-fueled capsule assemblies, ORNL-MTR-LT-L and 47-5,
were built to study the formation of CF4 in the.gas over fissioning MSRE
fuel containing submerged graphite. In assembly 47-4, four capsules con-
taining a graphite core submerged in fuel and two withvgraphite crucibles -
containing fuel were irradiated.
Assembly 47-4 was irradiated from March 15 to June 4, and it is now
undergoing postirradiation examination at ORNL. The maximum measured tem-
perature of the capsules was 1400 # 25°F during approximately 1500 hr of-
full-power steady-state reactor operation.. Sixty. of the 121 recorded tem-
perature changes of ~30°C or more included decreases to the solidus tem-
perature of the fuel salt.
Two capsules containing submerged graphite cores were installed in
assenbly L47-5 to permit gas sampling during irradiation. Additional sealed
capsules designed to provide a range of oxidation-reduction levels by
altering the accessibility of chromium metal to the fuel were included.
The range of the ratio of INOR-8 surface area to graphite surface area in
contact with the fuel is O to 46:1., Assembly L47-5 is scheduled to be ir-
radiated from September 17 to December 10, 1962.
Postirradiation examination of assembly L47-4 revealed that elemental
fluorine at pressures as high as 35 atmospheres was generated in some of
the rapidly frozen salt used in tests of the effect of radiation on evo-
lution of CF4 from fissioning fuel and graphite. The fluorine, undoubtedly
of radiolytic origin, appears in the frozen salt after shutdown and is
possibly the main causative agent of the CF4 in the capsules that contained
large quantities of CF4. Since capsules of different configuration in the
same lrradiated assembly showed widely divergent behavior, the undesirable
products may be strongly dependent on some incidental effect, such as the
ix
freezing history of the capsule. Present indications are that the fluo-
rine problem will not constitute a severe threat to the reactor operation.
Tests are in progress (ORNL-MTR-47-5) to obtain direct confirmation of
the evidence for a negligible concentration of fluorine in the molten
fuel.
6. Chemistry
A detailed examination of the U50°C contour in the LiF-BeFs-ZrF, ter-
nary system suggests that 67 mole % LiF, 29 mole % BeFz, and 4 mole % ZrF4
should be a suitable solvent for UFs in a simplified fuel that contains
no ThFy. A fuel based on this solvent, LiF-BeFp-ZrF.-UF, (66.85-29-4-0.15
mole %), has an estimated melting point of 445°C. This composition has
a density of 2.15 g/cm® at the operating temperature. _
The eutectic 1n the system LiF-UF4 appears to be useful as a concen-
trate (27 mole % UF4; mp, 527°C) for fuel makeup. The amount and nature
- of segregation on freezing of MSRE-type fuels are tolerable.
Experiments to demonstrate the reaction of CF, with MSRE systems gave
positive indications, mainly at 800°C. Presumably, they would provide
more conclusive results at higher temperatures than the 600 to 800°C range.
Studies of the cleanup of graphite and of fuel continued and efforts
to improve analytical aspects of MSRE fuel technology were directed toward
oxygen determinations in fuel and in graphite and toward homogenization
of radioactive samples of fuel.
T. Fuel Processing
Work on the detailed design of the MSRE fuel-processing system was
started. The system provides for oxide removal from the salt and uranium
recovery. A simplified flowsheet was prepared.
8. Engineering Research on Thermophysical Properties of Salt Mixtures
The liquid-state enthalpy and the viscosity of a LizsC0a-NasCOz-KCOa
(30-38-32 wt %) mixture proposed for use in out-of-pile studies relating
to the MSRE were experimentally obtained. Unusual scatter in the data
warranted only a linear fit of the enthalpy data. The derived heat ca-
pacity over the temperature span 475 to T715°C is therefore given by the
constant value 0.413 cal/g-°C. The kinematic viscosity was found to vary
from 16.5 centistokes at 460°C to 3.1 centistokes at T15°C. An estimate
of the mixture density as a function of the temperature allowed prediction
of the absolute viscosity.
THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
xi
CONTENT'S
------------------
PART 1. MSRE DESIGN, ENGINEERING ANALYSIS,
AND COMPONENT DEVELOPMENT
1. MERE DESIGN .....ciitiiieiniiierennnennnnns
Design Status ....... . i,
Reactor Procurement and Installation ......
Major Modifications to Building 7503 ...
Construction QOutside Building 7503 .....
Procurement of Materials ...............
Fabrication of Components ..............
Reactor Instrumentation and Control Systems
------------------
------------------
------------------
------------------
Layout of Instrumentation and Control System .............
Design Status ........ ... i,
Procurement Status ........ i v
2. MSRE REACTOR ANALYSIS .....cvvivinnenennnn.
Nuclear Accident Analyses .........ccieiuunn
Calculational Procedures .........oeveee,
------------------
------------------
------------------
------------------
Results of Fuel Pump Power Failure Analysis ..............
Effects of Cold-Slug Accidents .........
Results for Filling Accidents ..........
------------------
Effect of Uncontrolled Withdrawal of Rods ................
Effect of Graphite Movement ............
Results of Concentrated Fuel Addition ..
Reactor Statics Calculations ..............
Criticality Calculations ............ ...
Flux Distributions ............ ...
Power Density .......... ... i,
Steady-State Fuel and Graphite Temperatures
Temperature Distributions ..............
Average Temperatures .............c.....
Reactivity Coefficients ...................
Temperature Coefficients ...............
Power Coefficient .......... ... ... ... ...
Effective Delayed-Neutron Fractions .......
Reactor Kinetics Code Development .........
3. COMPONENT DEVELOPMENT ...........c.oieuinine...
Freeze-Flange Development .................
Freeze-Flange-Seal Test ................
Thermal-Cycle Test Loop ................
Freeze Test in Thermal-Cycle Test Loop .
------------------
oooooooooooooooooo
------------------
------------------
------------------
------------------
------------------
------------------
------------------
------------------
------------------
------------------
------------------
------------------
Test of a Freeze Flange in the Prototype-Fuel-Pump
Testing Facility ....... ..o,
MSRE Control Rod ...ttt nnnennnan
------------------
------------------
iii
Heater Tests .......
Pipe Heaters ....
.........................................
-----------------------------------------
Activation Analysis of Insulating Materials ..............
Drain-Tank Coolers .
-----------------------------------------
Sampling and Enriching System ....... .. it
Detail Design ...
-----------------------------------------
Mockup of Sampling and Enriching System ..................
Core Development ...
Model Operations
-----------------------------------------
-----------------------------------------
Velocity Measurements .........ciiiiiiiireninrinninnnnas
Measurement of Heat Transfer Coefficients ................
Experiments on the Behavior of Solids ........... ... ...
MSRE Engineering Test Loop (ETL) . vviiiiiteerinennnnneenns
Frozen-Salt-Sealed Graphite-Container Access Joint .......
Salt Composition
HF Treatment ....
-----------------------------------------
-----------------------------------------
Cold-Finger Collections in Cover Gas ...... . ..ot iiivnnnn
ETT, Graphite Treatment ...ttt ittt tiontianeennnros
MSRTE Maintenance ...
-----------------------------------------
Placement and Removal of Freeze-Flange Clamps ............
Miscellaneous Flange-Servicing Tools ..........coiviiivenn
Remote Viewing ..
-----------------------------------------
Portable Maintenance Shield ........c.ii ittt inntnnenenns
Brazed-Joint Development .. ...ttt i i
Brazed-Jdoint Fabrication .....c. it ittt ineteineneeoonns
Brazed-Joint Salt
Y= v
Mechanical-Joint Development ......... ... .. i,
Pump Development ...
-----------------------------------------
Fuel Pump Design and Fabrication .......... ... .
Coolant Pump Design and Fabrication ............ ... v
Design and Fabrication of Lubrication Stands for Pumps ...
Lubrication-Fump IEndurance Test .............. ... v
Drive Motor Deoign and Fabrication i..:i:iivisssisisssivessas
Test Pump Fabrication ..........ciiiiiiiiiiiiiiiiennns
Test Facility Construction ......... ... BT
Hydraulic Performance Tests ........cc i,
PKP Pump Hot Endurance Test ... i,
Test Pump With One Molten-Salt-Lubricated Bearing ........
Instrument Development ......... ... ittt innnnanns
Single-Point Liquid-Level Indicator ............ . ciiuie.n..
Pump-Bowl Liquid-Level Indication .............ciiiie..n.
Single-Point Temperature Alarm System ....................
Tenperaturc DeamIeT . ...ttt it it i i ettt i e e
Thermocouple Development and Testing ........... ... . ...,
PART 2. MATERIALS STUDIES
METALLURGY .........
Corrosion Effects of
-----------------------------------------
CF L o e s
Welding and Brazing Studies ........iiiii ittt
Heat Exchanger Fabrication ............ it nans
Remote Brazing ..
Welding of INOR-8
-----------------------------------------
----------------------------------------
-
46
46
47
48
49
49
49
49
49
50
51
52
53
53
54
56
56
58
59
59
60
60
60
61
61
62
62
62
62
62
63
63
63
63
63
65
66
66
66
66
68
68
ran
V%
87
87
88
88
92
92
xiii
Mechanical Properties of INOR-8 ... .... . ciiiiiinnen..
Properties of Reactor-Quality INOR-8 ...............
Thermal Fatigue of INOR-8 .......cciiiiiiiiinnnnnnn
Graphite Studies ... ..t i i it i e i
Evaluation of Grade TS-281 Graphite ................
Effects of Thermal Decomposition Products of
NH,F-HF on Graphite-INOR-8 Systems ................
Fabrication of Gd;03 and Gds03—Al1,03 Pellets ..........
IN-PILE TR S .. ittt et ettt et et e v s ssaansaenonnsensnns
ORNL-MIR-47 Molten-Salt Irradiation Experiments .......
Experiment ORNL-MIR-47-4 ... ... iuiiiinnnnennennnnnn.
Experiment ORNL-MIR-47-5 ... ... ..t iniiiniinnnan.
Postirradiation Examination of Experimental Assembly
ORNL-MIR =4 7=3 .. ittt ittt it tins e iaane e,
Chemical Analyses of Irradiated Fuel for Corrosion
Products . ... . i e
Distribution of Radicactivity and Salt in Irradiated
Graphite ... .. i e
Postirradiation Examination of Experimental Assembly
ORNL-MIR -4 74 i ittt et ettt et et s e
Description of Capsule ..........ciiiiin e,
Fabrication and Loading of Capsules ........... ...
Fuel o e i i e e e
Graphite ... . i i i i e e e e e
Decay Bnergy ... e e e e
Irradiation and Temperature Data ...................
Production of Xenon and Krypton ....................
GasS ANa Ly Se S vt ittt e i et e e e e
Discussion of Results ........ ... .,
Phase Equilibrium Studies .......c.cuiii ittt nnnnnens
The System LiF-BeFo-ZrFs; . ... i iiiiiiaen..
The System LiF-BeFp-ZyF 4-ThF4-UFs ..o iivn...
Li¥-UF, Eutectic as a Concentrated Solution of UF,
for Fuel MaKkeup ..... vt ittt it nnnaeeennns
Fractionation of LiF-BeF,-ZrF,-ThF,~-UF, on Freezing
Crystal Chemistry ........ ... i,
Oxide Behavior in Molten Fluorides — Dehydration of LiF
Physical Properties of Molten Salts ...................
Density of LiF-BeFo-2rF4-UFys ...ttt
Estimation of Densities of Molten Fluorides ........
Graphite Compatibility ....... ... i .
Removal of Oxide from Graphite Moderator Elements ..
Behavior of CF, in Molten Fluorides ................
Analytical Chemistry . ... ittt ten it an
Determination of Oxygen in MSRE Fuel Mixtures ......
Determination of Oxygen in Graphite ................
Homogenization of Radiocactive MSRE Fuel Samples ....
oooooo
------
......
oooooo
------
------
------
------
------
------
------
------
------
oooooo
------
------
oooooo
------
95
95
95
96
96
97
98
100
100
100
102
105
105
106
106
108
108
10%
.109
110
110
110
112
115
117
117
117
118
119
121
121
122
123
123
123
125
125
128
130
130
131
131
FUEL PROCESSING
Xiv
---------------------------------------------
ENGINEERING RESEARCH ON THERMOPHYSICAL PROPERTIES OF
SALT MIXTURES .« v otvvee ettt et e e e e e e e e e e e e
Enthalpy
Viscosity
----------------------------------------------------
---------------------------------------------------
133
135
135
136
PART 1. MESRE DESIGN, ENGINEERING ANALYSIS,
AND COMPONENT DEVELOPMENT
~ THIS PAGE
WAS INTENTIONALLY
LEFT BLANK
1. MSRE DESIGN
Design Status
Design work on the MSRE was essentially completed. There remains
only final revising of system layout and design drawings and completion
of the electrical design. The design report, in which all engineering
calculations and analyses of the systems are presented, is presently be-
ing compiled. Much of the design work remaining to be completed involves
incorporation of development work into final design drawings. An example
of such a design is the removable salt-pipe heaters and insulation. Final
test evaluations of two different concepts of such removable insulated
heater sections are nearing completion. Design drawings of these units
must be completed after these tests indicate which type will be used in
the system.
Another item that awaits final test evaluation before the design can
be completed is the control rod drive. A model incorporating all the
principles has been operated successfully, and testing of an actual pro-
totype unit will permit the design to be finished. Such a prototype 1is
being ordered.
All layouts for the three major areas, reactor cell, drain tank cell,
and coolant cell, are complete, The variocus penetrations into these cells
have also been designed. The layout of interconnecting gas, water, elec-
trical, and instrument lines between these cells is nearing completion.
Considerable effort was devoted to the design of the containment ves-
sel, and all parts of this design were completed. Several methods of ef-
fecting a closure with the seal membrane that welds to the steel shell
were analyzed before an acceptable concept could be detailed. The pe-
riphery of the containment vessel just below the closure flange was re-
inforced with a circumferential steel ring to bring the stresses within
limits at design-point pressure. This pressure was dictated by the maxi-
mum credible accident. The vapor-condensing system, which ensures toler-
able pressures within the cell in the event of the maximum credible acci-
dent, was designed.
Since the molten-salt system employs electrical heat to bring all
components to the operating temperature, the electrical distribution for
this heater network is rather elaborate. This electrical system is about
40% designed. The heater control centers are complete. Conduit and
cable-tray layouts are 6U% complete. 'I'ne design ot moditications to
existing auxiliary diesel power controls are 60% complete. All electri-
cal designs are scheduled to be coumpleled Ly March 1, 19G3.
Design drawings for the charcoal-adsorber system for the offgas are
finished. Layout drawings of offgas piping in the reactor cell, drain tank
cell, and special equipment room are 95% complete. - Very little remains
to be done to bring the design of the entire gas system to completion.
4
The design of the jigs and fixtures for the assembly of the initial
and replacement components for the test cell was completed. The compo-
nents, piping, and flanges are supported by adjustable supports that du-
plicate or resemble the test cell structure and are positioned precisely
by optical tooling. Design work on the fixture for the assembly of the
drain tanks and flush tank is in progress.
Completion of the items mentioned above will complete the design of
all major equipment and facilities, including the maintenance control
room, the remote crane control, the television viewing devices, and the
remotely operable lifting tongs. The design of the work shield, protec-
tive environment enclosure (standpipe), tools, and operating procedure