Agenda

  • Phase 10A Scoping

Administrative

  • Phase 10A Scoping
    • Tasks that have clear deliverables were changed to deliverables based cost structure
    • RSG Scope
      • Task 1: Code Review and Software Development Support
        • Reduced from past years to ensure funds are spent and have less time to spend funds
      • Task 2: PopulationSim Dependency Updates
        • RSG needs to respond to comments in scope
      • Task 3: Sub-Model Preprocessing and annotated consistency
      • Task 4: Software Design and Prototyping for Choice Simulation and Error Terms
        • RSG is lead on this task and has set deliverables
    • CS Scope
      • Task 1: Project Management
        • Assumes that we will meet less than twice a week
      • Task 2: Code Review and Software Development Support
        • Reduced from past years to ensure funds are spent and have less
      • Task 3: Specification Performance Analysis Tool
        • Profiler tool will work for legacy code; Getting to work on Windows directly may be difficult
      • Task 4: Skim variable input checks
      • Task 5: Input file validation
      • Task 6: Software Design and Prototyping for Choice Simulation and Explicit Error Task
        • Remain as time and materials-based given support role
    • WSP Scope
      • Task 1: Code Review and Software Development Support
      • Task 2: Roadmap
      • Task 3: Software Design and Prototyping for Choice Simulation and Explicit Error Task
        • Remain as time and materials-based given support role
    • Schedule
      • Consultants to identify duration of time to complete; when it will kick-off and when it will be completed
      • Will inform look ahead for scheduling of meetings
        • Provide input by next week's meeting
  • Overall budget
    • Total income: $490,000
    • AMPO OH (15%): $73,500
      • Double what has been allocated before
    • Contingency (32.5%): $159,250
    • CS Phase 10 TO: $95,152
    • WSP Phase 10 TO: $67,474
    • RSG Phase 10 TO: $94,066
    • Available: $558
  • Other
    • For Phase 11, Looking likely that 1 agency will leave and 1-2 will join
    • Next Tuesday meeting: Talk about schedule; Admin transition update
    • Cancel Thursday's meeting
    • There is an ActivitySim implementation in Istanabul; Will present to group at future meeting
      • Worked on it full-time for 6 months
      • May join consortium
    • EU may join as well
      • ActivitySim is becoming preferred option