Scheduling and Work Breakdown
Shay Kalyan edited this page Aug 21, 2014
·
4 revisions
The project schedule and resource allocation can be viewed via the Microsoft Project file linked on this page. The key milestones are listed below.
Milestone | Description | Date |
---|---|---|
Complete Project Plan | Submission of Project Plan | 07/08/14 |
Alpha Release | Release of a working progress demo showcasing simple robot behaviour | 15/08/14 |
Final Release | Release of a final version of the simulation illustrating group robotic behaviour meeting the requirements set | 29/08/14 |
Click here to download the Project file.
Project File created and maintained by Tommy, Akshay and Matthew.
- 21/08/14
- Added Random Event and Scheduler design and implementation tasks
- Updated resource assignment for Weekly Presentation 4
- Reassigned resources for certain tasks to reflect current allocations
- Removed Weekly Presentation 5
- 12/08/14
- Updated resource allocation for Weekly Presentation 2
- Added ongoing documentation tasks in between major milestones
- 04/08/14
- Assigned resources to tasks